Ishpeming Update
June 1, 2009

ISHPEMING PROJECT UPDATE

After completing extensive analysis of the “alpha” designed blades and a test lift in April, MTI has made a business and technical decision to produce and install a significantly re-designed “beta” blade. The beta blade more closely mirrors the production blade design, which will enable certification. The beta blade is more than 40 times stiffer than the alpha design enabling a more efficient installation and improvement in performance.

In addition, the review of the test lift has identified a less costly and faster method to hoist the blades atop the tower. A special lifting device has been designed and is being built that will result in a much improved lifting procedure.

Cranes will be relocated to another job until construction resumes. Blade delivery and installation completion dates are estimated at six to eight weeks.

 

 

Ishpeming Update
April 17, 2009

MTI UPDATES ISHPEMING WINDSTOR WIND TURBINE INSTALLATION

BRIGHTON, MI – MTI Energy Management / Lighting Specialists has advised McKenzie Bay International Ltd (“MKBY:OTC.PK)that the WindStor® installation process at Pioneer Bluff Apartments in Ishpeming, Michigan continues to advance towards completion according to plan. MTI has taken many extra steps to ensure the successful completion of a renewable energy system where construction began and then delayed more than two years ago.

Most of the components that were not installed until this year have been in storage during this time.  To be certain that system integrity is maintained and safe operation is achieved; MTI is testing all parts and components multiple times during the completion process.  Testing has resulted in re-engineering parts and processes such as changing nuts and bolts to stainless steel, revising tolerances to higher standards, and identifying and correcting numerous oversights.

The blade installation is the final and most complex process requiring the greatest amount of planning and design. Thus far, one blade has been trial-lifted, temporarily installed, and taken back down.  MTI has conducted blade stress analysis tests based on the trial-lift and have determined that a custom-designed lifting support brace will be necessary for elevating the blades in a more efficient, less costly and safer manner.  A re-usable custom support brace is currently being designed and manufactured.  MTI anticipates the brace will be available in May for a successful completion.

MTI reports that an improved blade design, constructed of a composite material, will be utilized for future installations and will eventually replace the blades at Pioneer Bluff.  These blades will be implemented as soon as the manufacturing process is completed and a manufacturing source is identified.


March 18, 2009

McKenzie Bay International (MKBY), Settles MTI Lawsuit; Appoints New Board
 


Listen to our R.A.M.P. radio spots. Click the links below

MTI Energy Management / Lighting Specialists, Inc.
now offers performance contracting for lighting.

MTI is Michigan and the Midwest's premier energy management and lighting retrofit company. We specialize in energy-effective lighting upgrades for commercial and industrial businesses, reducing your overall operating expense and guaranteeing you energy Savings of up to 50% or More on your monthly lighting electrical costs. Our professional team of lighting consultants and technicians will custom design an energy-effective lighting system to meet your specific needs.

Does your facility still have any of these energy wasters?

T12 fluorescent lamps with magnetic or electronic ballasts
1st generation 700 series T8s with generic electronic ballasts
Metal Halide or High Pressure Sodium Fixtures
Fluorescent or incandescent exit signs
Standard halogen MR16, PAR30 or PAR38 accent lighting
Typical incandescent light bulbs

MTI can help you save energy and improve the environment by replacing those old products.  These energy efficient equipment replacements can be very cost effective, especially when tax credits are included.

Call us today and discover how your entire lighting project
can be financed out of your savings!

MINIMIZING Energy Consumption
While
MAXIMIZING Profitability

Benefits

Increases safety and security in hazardous working areas
Minimizes maintenance costs and energy consumption
Maximizes lighting system performance
Reduces costly recycling charges
Ensures EPA compliance for disposal of lighting components
Enhances visual appearance
Improves light levels
Increases productivity
Improves profitability
Eases eye fatigue

 


Home : About MTI : Testimonials : LightScape: R.A.M.P. Program Contact Us : In The News

About Financing : New Products : Energy News : Our Mission

7627 Park Place Suite 101, Brighton, Michigan 48116
Phone: 248-446-9502  Fax: 248-446-9503
R.A.M.P. Program: 1-800-507-RAMP

1999 - 2007 © MTI Lighting Specialists. All rights reserved.   Privacy Statement