Home
About MTI
Testimonials
LightScape SM
R.A.M.P. SM
Case Studies
Before and After
Strategic Alliance Partners
Contact Us
In The News
About Financing
Our Mission
News From Michigan Green
(UPDATED 06-23-10)
Ishpeming Project Progress

MTI participates in the following Utility Rebate Programs


Consumers Energy Efficiency Program


DTE Energy Efficiency Program

Ishpeming WindStor Progress

---MTI Youtube Link---


June 22, 2010

All Installed Blades viewed from distance


June 21, 2010 - Photos courtesy of Dave Nelson

3rd Blade Installed


June 20, 2010 - Photos courtesy of Dave Nelson

2nd Blade Installed


June 19, 2010 - Photos courtesy of Dave Nelson

2nd Blade Installation

1st Blade Installed


June 18, 2010 - Photos courtesy of Dave Nelson

1st Blade Installation


June 16, 2010

Ishpeming project - lift device testing


June 15, 2010

Ishpeming project progress videos and photos

See All Videos (MTI Youtube Link)

 


June 13, 2010

WindStor Wind Turbine Blades U.P. Bound

At 1:00 PM EST Sunday, June 13th, blades and lifting rig for the first commercial WindStor® vertical-axis wind turbine departed MTI's shop in Brighton, Michigan for the installation at Pioneer Bluff Apartments in Ishpeming, Michigan. Completion of the installation will begin in earnest Monday morning, June 14th.

All that remains to complete the installation is to attach the three blades to the tower. Blades were each transported in three sections that will be assembled onsite before being lifted into place with a unique "patent pending" lifting rig designed specifically for lifting vertical-axis wind turbine blades.

The lifting rig had to be transported in pieces much like a giant erector set. A crane will assemble the lifting rig and will first perform a test lift prior to installing the blades. The lifting rig has four clamps that will carry the blade as a passenger into place atop the tower.

Once completed, an extensive testing process will begin immediately and last for a few months as part of the certification process before WindStor® can be mass produced.

"If everything goes as planned and the weather cooperates, the installation could be completed by Saturday", said Bryan Zaplitny, President of MTI Energy Management / Lighting Specialists Inc. "This installation will signal the start of a new dimension for distributed generation from renewable resources at the customer's facility."

Blades Leaving MTI - Video

More Photos- Blades and Lift Crossing the Mackinac Bridge


June 11, 2010

Ishpeming Wind Turbine project update

BRIGHTON - The final installation and construction of the Ishpeming Wind Turbine project continues on Monday, June 14th with the arrival of the lifting rig and blade sections.

The trucks were loaded in Brighton on Friday, June 11th. Pictures and video follows.

The lifting rig is a tool that will be re-used for future turbine installations. Once the lifting rig is assembled the blade sections will be joined and raised. The goal is to have the blades installed by month end.

We also offer an update on our construction electrical partner, Dave Nelson of Nelson Electric Service.

As the process played out in the restructuring of the companies involved and the project in Ishpeming, it was decided to contact Dave Nelson of Nelson Electric Service, Inc. of Ishpeming.

Nelson Electric Service, a 60 yr old business, had been heavily involved in the design of how the wind turbine would tie into the Ishpeming Housing Commission building power grid to supplement the utility when the project was started in 2006.

Dave had retired in April of 2008, but had retained his licenses to perform electrical work in the state of MI. The open electrical permit for the project was still under the license of Nelson Electric Service and remained so for the duration of the project.

Dave decided to come out of retirement (and forego his plans to observe the winter of 2008-09 from a warm climate) to help finish this historical undertaking and in his words, "One of the most interesting projects he had worked on in his 35 yrs in the business." The task was given to Dave to assemble an electrical team to see the project through. He decided that instead of starting up payroll and other insurances required for Nelson Electric to proceed, he would contact Dan Audette, owner of Code Electric of Marquette, MI to see if Dan would agree to provide a labor source to supply a man, and sometimes two, to finish the project.

Dan agreed to take part. The project would then proceed under the direct supervision and instruction of Nelson Electric Service for the remainder of the project.

Next, he asked his brother, Steve, if the company Steve used to work for, MJ Electric from Iron Mountain, MI might be able to help. MJ was contacted to see if they could provide the electrical engineering and data communications services that would be necessary to complete the project.

They agreed to do so, and Joey Wade of MJ Electric was brought onboard and proved to be a phenomenal asset to the project. Joey is the chief engineer of MJ's industrial, power, and controls division. His expertise has been absolutely critical to the successful outcome of the wind turbine project in Ishpeming. Among numerous other engineering contributions, Joey designed the electrical wiring layout for the metering cabinets along with the brake alteration cabinet which Dave then built in his basement shop.

The many unresolved issues of the electrical design that came to light were tackled and sorted out one by one.

Finally, it was time for the blades to go on, and at that point, it was realized there was a design flaw in the blades and they weren't going to be able to be used. The job then came to a stop, again, while different engineering strategies were employed to try and rectify this latest problem.

Several months went by, and finally Dave got a call from Bryan Zaplitny last summer saying new blades had been built and the job was on again. Unfortunately, October 30, 2009, Dave was diagnosed with stage 3 Esophageal Cancer, one of the most rare and deadly cancers in the world. He has now been through treatment and had surgery February 24, 2010. Many complications have arisen due to the surgery and Dave's roll in the project has become limited. The Nelson Electric Service Inc. Electrical permit still remains open on the job. Dave has always wanted to be part of the completion of this project. He has always said it was one of the most interesting projects he'd ever been involved with in his 35 years in the electrical trade. Even in his limited capacity, Dave will be there, and this will become the Nelson Electric Service Inc. final job. Dave's dad would have been pleased to be a part of a project like this. Dave used his dad's homemade pulling wheel to get the 4/0 Armored main generator cable up to the top of the tower 3 yrs ago. It was just taken down a couple weeks ago when work, once again, was resumed.

Dave Nelson Video link

Blade loading photos

Blade loading video
 


January 8, 2010

Ishpeming UPDATE

View the Ishpeming update PDF file and associated video files through the links below:

Ishpeming Update

Blade Test Assembly video

Blade Lift animation

Blade Clamp Release animation
 


August 14, 2009

BETA BLADE ARRIVES

The first beta blade arrives for additional processing.  The new and improved blade will be foamed and skinned.  More developments to follow.


June 1, 2009

ISHPEMING PROJECT UPDATE

After completing extensive analysis of the “alpha” designed blades and a test lift in April, MTI has made a business and technical decision to produce and install a significantly re-designed “beta” blade. The beta blade more closely mirrors the production blade design, which will enable certification. The beta blade is more than 40 times stiffer than the alpha design enabling a more efficient installation and improvement in performance.

In addition, the review of the test lift has identified a less costly and faster method to hoist the blades atop the tower. A special lifting device has been designed and is being built that will result in a much improved lifting procedure.

Cranes will be relocated to another job until construction resumes. Blade delivery and installation completion dates are estimated at six to eight weeks.

April 17, 2009

MTI UPDATES ISHPEMING WINDSTOR WIND TURBINE INSTALLATION

BRIGHTON, MI – MTI Energy Management / Lighting Specialists has advised McKenzie Bay International Ltd (“MKBY:OTC.PK)that the WindStor® installation process at Pioneer Bluff Apartments in Ishpeming, Michigan continues to advance towards completion according to plan. MTI has taken many extra steps to ensure the successful completion of a renewable energy system where construction began and then delayed more than two years ago.

Most of the components that were not installed until this year have been in storage during this time.  To be certain that system integrity is maintained and safe operation is achieved; MTI is testing all parts and components multiple times during the completion process.  Testing has resulted in re-engineering parts and processes such as changing nuts and bolts to stainless steel, revising tolerances to higher standards, and identifying and correcting numerous oversights.

The blade installation is the final and most complex process requiring the greatest amount of planning and design. Thus far, one blade has been trial-lifted, temporarily installed, and taken back down.  MTI has conducted blade stress analysis tests based on the trial-lift and have determined that a custom-designed lifting support brace will be necessary for elevating the blades in a more efficient, less costly and safer manner.  A re-usable custom support brace is currently being designed and manufactured.  MTI anticipates the brace will be available in May for a successful completion.

MTI reports that an improved blade design, constructed of a composite material, will be utilized for future installations and will eventually replace the blades at Pioneer Bluff.  These blades will be implemented as soon as the manufacturing process is completed and a manufacturing source is identified.


April 6, 2009

The wind turbine installation continues to advance through planned steps at Pioneer Bluff Apartments and is nearing completion.

A trial blade installation was performed on Wednesday and Thursday last week. We are now making final adjustments to the blade installation and lifting process.

The next to last mechanical component to be installed is a German designed braking system. Technicians are awaiting visa approval for their entry into the USA to certify that the brake system meets their technical specifications.

Blade installation will proceed after final adjustments are completed and the installation of the braking system. We have completed all of our testing for this phase. Weather permitting the installation will proceed after the Easter holiday.


March 27, 2009

Turbine shaft Cap installation - the snow returns

 


March 26, 2009

More turbine shaft installation


March 25, 2009

More turbine shaft installation


March 24, 2009

Blade Preparation


 


March 20, 2009

Generator Installed & Turbine Shaft Installation in progress

One of the Village People

Extending Crane


March 18, 2009

McKenzie Bay International (MKBY), Settles MTI Lawsuit; Appoints New Board

 


March 9, 2009

Platform hoisting


 


March 3, 2009

Cranes arrive onsite

 


February 18, 2009

Blade sections unloaded in Ishpeming

 


February 17, 2009

Blades sections skinned, painted, loaded and shipped


 

January 12, 2009
 

Street Closing Approved for Construction Phase of wind turbine project at Pioneer Bluffs Apartments in Ishpeming.


December 22, 2008

Blade completion in process.  Happy Holidays!









Another shipment arrives


December 19, 2008

More components for the WindStor installation at Pioneer Bluffs in Ishpeming, MI are scheduled to arrive by truck on Monday, December 22, 2008.


December 16, 2008

Wind turbine nears completion

Pioneer Bluff in Ishpeming is ready to finish their form of alternative energy.

ISHPEMING -- After two years of waiting, a senior housing complex will soon be using cheaper, alternative energy.

Pioneer Bluff in Ishpeming received some of the parts that will complete their wind turbine project.

So far, only blade hubs and steel pipes have been delivered.

They'll be assembled to the tower sitting in front of the 88-unit apartment building.

MTI Energy, which took over the project, says it will provide 500,000 to 750,000 kilowatt hours a year and should take no more than a month to complete, weather permitting.

Watch video

Tuesday, December 16, 2008 at 6:04 a.m.
WLUC TV6 

Original link: http://www.uppermichiganssource.com/news/news_story.aspx?id=235932


December 16, 2008

Wind project getting off ground

By JOHANNA BOYLE, Journal Staff Writer

ISHPEMING - The wind turbine that will power the Pioneer Bluffs Apartments is one step closer to the start of construction.

The bulk of the two truckloads of equipment, which included the long inner and outer shafts of the turbine, arrived in Ishpeming Monday.

"I'm hoping to assemble in January," said Bryan Zaplitny, CEO of MTI Energy Management, the downstate company which designed the turbine. "We're sticking with it," despite predicted cold temperatures.

When fully constructed, the turbine will stand 90 feet above the already-built tower and will feature an 85-foot sphere to house the turbine blades.

In addition to Monday's deliveries, Zaplitny said four more trucks are expected, with two possibly arriving before Christmas.

One of the next shipments should include the turbine blades, which are being constructed, Zaplitny said. Once installed, the weather will not affect the blades' finish, he said. However, in extremely cold weather, workers will have to be careful during the unloading process when the turbines could be damaged.

Following the installation, the turbine will go through a series of tests, lasting about a month, before the apartment complex can begin to use the power, Zaplitny said.

The turbine will help lower the Pioneer Bluffs energy costs and will keep that energy rate stable for about 15 years, Zaplitny said. The turbine should produce 500,000 to 700,000 kilowatts annually.

Yalmer Mattila Contracting, the Houghton-based company that will be installing the turbine, plans to use a five- or six-person team to complete the assembly, said Jeremy Mattila, equipment operator for the company.

Although the project has been stalled for various reasons over several years, Zaplitny said Yalmer Mattila has been helpful and easy to work with.

"They've just been real good about everything. It instills a lot of faith in the people of the U.P. for sticking with it," he said.


Check out the video - Video Exclusive

By JOHANNA BOYLE, Journal Staff Writer
POSTED: December 16, 2008

Original story link:http://www.miningjournal.net/page/content.detail/id/519939.html?nav=5006


December 16, 2008

Wind turbine nears completion
Pioneer Bluff in Ishpeming is ready to finish their form of alternative energy.

ISHPEMING -- After two years of waiting, a senior housing complex will soon be using cheaper, alternative energy.

Pioneer Bluff in Ishpeming received some of the parts that will complete their wind turbine project.

So far, only blade hubs and steel pipes have been delivered.

They'll be assembled to the tower sitting in front of the 88-unit apartment building.

MTI Energy, which took over the project, says it will provide 500,000 to 750,000 kilowatt hours a year and should take no more than a month to complete, weather permitting.

Watch video

Tuesday, December 16, 2008 at 6:04 a.m.
WLUC TV6 

Original link: http://www.uppermichiganssource.com/news/news_story.aspx?id=235932


December 16, 2008

Wind project getting off ground

By JOHANNA BOYLE, Journal Staff Writer

ISHPEMING - The wind turbine that will power the Pioneer Bluffs Apartments is one step closer to the start of construction.

The bulk of the two truckloads of equipment, which included the long inner and outer shafts of the turbine, arrived in Ishpeming Monday.

"I'm hoping to assemble in January," said Bryan Zaplitny, CEO of MTI Energy Management, the downstate company which designed the turbine. "We're sticking with it," despite predicted cold temperatures.

When fully constructed, the turbine will stand 90 feet above the already-built tower and will feature an 85-foot sphere to house the turbine blades.

In addition to Monday's deliveries, Zaplitny said four more trucks are expected, with two possibly arriving before Christmas.

One of the next shipments should include the turbine blades, which are being constructed, Zaplitny said. Once installed, the weather will not affect the blades' finish, he said. However, in extremely cold weather, workers will have to be careful during the unloading process when the turbines could be damaged.

Following the installation, the turbine will go through a series of tests, lasting about a month, before the apartment complex can begin to use the power, Zaplitny said.

The turbine will help lower the Pioneer Bluffs energy costs and will keep that energy rate stable for about 15 years, Zaplitny said. The turbine should produce 500,000 to 700,000 kilowatts annually.

Yalmer Mattila Contracting, the Houghton-based company that will be installing the turbine, plans to use a five- or six-person team to complete the assembly, said Jeremy Mattila, equipment operator for the company.

Although the project has been stalled for various reasons over several years, Zaplitny said Yalmer Mattila has been helpful and easy to work with.

"They've just been real good about everything. It instills a lot of faith in the people of the U.P. for sticking with it," he said.


Check out the video - Video Exclusive

By JOHANNA BOYLE, Journal Staff Writer
POSTED: December 16, 2008

Original story link:http://www.miningjournal.net/page/content.detail/id/519939.html?nav=5006


December 11, 2008

The first two truckloads of components for the WindStor® installation at Pioneer Bluff Apartments in Ishpeming, Michigan are scheduled to arrive on Monday, December 15th, 2008.
 


December 8, 2008

Work to resume on wind turbine project

By JOHANNA BOYLE, Journal Staff Writer

ISHPEMING - Developers of the wind turbine project at Ishpeming's Pioneer Bluff Apartments hope to have the structure producing energy early next year.

Construction on the WindStor turbine, which was supposed to have been completed in 2006, should begin by the end of this month, according to the Ishpeming Housing Commission and MTI Energy Management CEO Bryan Zaplitny.

"We'd like to let everyone know we're moving forward," Zaplitny said.

Materials for the construction, including the turbine's blades, should be arriving in Ishpeming by Dec. 17, he said.

The project was stalled for the past two years due to a number of factors, he said. Although he would not discuss those factors in detail, Zaplitny said a lawsuit between MTI and McKenzie Bay and YA Global, two companies that were associated with MTI, was not the main factor.

"The issues are being straightened out," Zaplitny said.

Despite the cold weather, MTI is determined to get the project finished, Zaplitny said.

"I don't care if there's three feet of snow on the ground," he said. "That project will be done even in the harshest conditions."

Once it is functional, the turbine will provide cheaper alternative energy to the residents of the 88-unit senior housing complex, said Evelyn Valente-Heikkila of the Ishpeming Housing Commission. The agreement is that MTI erects the turbine free of charge and the apartment complex purchase the power created, Valente-Heikkila said.

"I'm pretty optimistic" it will be completed, she said.

Article Photos

The tower for the planned wind turbine sits in front of Pioneer Bluff Apartments, a senior housing complex in Ishpeming, in March 2007. MTI Energy Management said it will resume working on the turbine this month. MTI plans on having the turbine operational early next year. (Journal file photo)

Original article location: http://www.miningjournal.net/page/content.detail/id/519550.html?nav=5001


November 24, 2008

CLEAN GREEN ENERGY ADVANCES RENEWABLE ENERGY PROGRAM WITH LAS VEGAS AREA SCHOOL DISTRICT

MTI ENERGY MANAGEMENT / LIGHTING SPECIALISTS MOVES FORWARD WITH ISHPEMING, MI WINDSTOR® WIND TURBINE INSTALLATION


Brighton, MI, November 24, 2008 -- Clean Green Energy, LLC (CGE) (www.cleangreenenergyllc.com) advances forward with the Nevada Renewable Energy at Schools Pilot Program at the Clark County School District (CCSD) in Las Vegas.

A team of nine professionals engineering the project were in Las Vegas the week of November 17-21, 2008 and worked with CCSD facilities management, site engineering, and maintenance personnel. During this first of a series of scheduled trips to Las Vegas, the goal was to select specific sites for integrated solutions to rising energy costs. CCSD extended extraordinary cooperation to CGE professionals in supplying vital information necessary to facilitate a successful project.

Bryan Zaplitny, CGE President said, "We are extremely excited about this Project EverGREEN Schools™ renewable energy program for the Clark County School District. We believe that this could become a model for all school systems as a cost cutting, green energy generation and education solution throughout North America. This extraordinary opportunity, in conjunction with the WindStor® vertical axis wind turbine installation in Ishpeming, Michigan, has resulted in numerous inquires worldwide about green energy solutions."

Mr. Zaplitny, also CEO of MTI Energy Management / Lighting Specialists, Inc. (www.mti-energy.com ) further added, "MTI continues to move forward with the completion of the Ishpeming, Michigan, Pioneer Bluffs Assisted Living Community's, WindStor® wind turbine project. We met with contractors on Friday, November 14, 2008 and significant progress was made with the fine tuning of the electrical system, which will be the hub of the turbine's wind generation capability. Engineers and electrical contractors are prepared to accept system components and begin final assembly operations in December, 2008."

For more information - email cge@cleangreenenergyllc.com


Ishpeming Update
November 3, 2008

We are preparing to begin shipping the final components necessary to complete the WindStor® installation at Pioneer Bluff Apartments in Ishpeming, Michigan.  As components are transported to Ishpeming, we will post photos of the events.

We are taking these steps to be prepared to complete the installation as quickly as possible after breaking escrow from the closing of the McKenzie Bay and YA Global agreements.  Winter weather conditions will not prevent our completion of the installation.


October 16, 2008

McKenzie Bay International (MKBY), MTI Energy & YA Global Agree to Settlement
 


Component Parts for Completion


Posted 9/30/2008
Turbine shaft end section for blade attachment and turbine top end cover with plates


Posted 9/30/2008
Turbine shaft sections w/flanges


Posted 9/30/2008
Close up of turbine shaft sections w/flanges


Posted 9/25/2008


Posted 9/11/2008


CLEAN GREEN ENERGY SECURES PARTNERS GREEN ASSETS


Message from Bryan Zaplitny - President/CEO MTI


 

Updates regarding the WindStor project in Ishpeming Michigan
 

August 25, 2008


At the request of McKenzie Bay International Ltd, MTI is respecting this request by removing the previously posted reports of progress regarding settlement agreements signed on August 21, 2008.



 

MTI vs. MKBY / WindStor -- MTI Files Complaint 12-28-2007

Please review the verified complaint filed by MTI on Dec. 28, 2007 at the link below this statement. This action was necessary to state the facts, to move toward the completion of Ishpeming, to protect MKBY shareholders and their investments. The following points will give the readers of this announcement greater details.

  1. MKBY/Windstor management has refused to communicate in any way (meeting in person-requested by MTI several times, phone, email, fax) since October of 2007 with MTI.
     
  2. MTI has expended substantial amounts of time and resources to complete the Ishpeming project. However, at every step in this process, MKBY/Windstor has interfered in this completion.
     
  3. MKBY stock issuance to MTI was to be used at MTI’s discretion to reduce outstanding debt and to negotiate vendor contracts. MKBY owed suppliers and contractors for work completed, in progress, or to be completed in order to finish the Ishpeming project.
     
  4. MKBY not only tried to break the contract with MTI and recall the entire stock issuance, but they also would not allow their engineers to continue working with MTI to complete the Ishpeming project.
     
  5. Despite all that has transpired, MTI would like to complete the Ishpeming project. They have invested heavily into the project, have arranged completion agreements with suppliers and contractors, and have enhanced the project with other renewable energy elements (solar with Uni-Solar and energy storage with Cobasys) that MKBY had nothing to do with. Even though MTI was only the sales agent for MKBY, they have taken on responsibility of completing the project with the full cooperation of the existing Board of Directors (which is the existing management of Mckenzie Bay). The people of Ishpeming, the city and, especially, the housing commission, have waited patiently for this project to be completed and MTI wants to honor their loyalty and commitment by finishing what was started (and should have been completed) two years ago.

View MTI's complaint filed 12-28-07
(4.15 MB allow time to load)



Home : About MTI : Testimonials : LightScape: R.A.M.P. Program Contact Us : In The News

About Financing : New Products : Energy News : Our Mission

7627 Park Place Suite 101, Brighton, Michigan 48116
Phone: 248-446-9502  Fax: 248-446-9503
R.A.M.P. Program: 1-800-507-RAMP

1999 - 2007 © MTI Lighting Specialists. All rights reserved.   Privacy Statement