Ishpeming WindStor Progress

January 18, 2010

Ishpeming Wind Turbine Work to Continue

ISHPEMING - Although it has been several months since area residents last saw activity at the site of the wind turbine near the Pioneer Bluffs Apartments in Ishpeming, the company developing the turbine said the work will be completed.

"We are about safety and producing something that will be a good product," said Bryan Zaplitny, CEO of MTI Energy Management based in downstate Brighton, which has been carrying out work on the turbine in cooperation with McKenzie Bay International. "There have been a lot of things that have been solved."

However, Zaplitny said a completion date has not been set.

"I'm not going to prematurely say anything," he said. "We're looking for a safe and successful completion rather than an arbitrary schedule."

Work crews were last at the site in April, when one of the 110-foot long blades was attached to the 162-foot tower that was completed earlier in the year. Following the test, the blade was removed for modifications.

Zaplitny said a new series of blades has been engineered and produced, offering more rigidity and eliminating concerns with the aluminum skin covering the blades. The new blade design reduced the weight of the three blades from 2,000 pounds each to 700 pounds.

With the new blades taken care of, MTI is working on the design and construction of a lifting rig to hold the blades steady while being lifted into the air and attached to the turbine tower.

The rig allows for the use of a single crane in the lifting process as opposed to the three needed in the original trial lift, providing more safety for those working on the structure, according to MTI.

The Ishpeming turbine is a prototype of the turbines MTI and McKenzie Bay hope to produce on a wide scale. It is expected to provide half the power needed to run the 88-unit facility.

At the Pioneer Bluffs Apartments, the turbine is being constructed on a power purchase agreement that calls for the Ishpeming Housing Commission to pay for the power, not the construction.

"They have zero dollars in this," Zaplitny said. "Nobody from the receiving site has spent any money."

In the future, it is hoped the wind turbines can be produced in different sizes for residential or business customers, depending on how much space they have and their power needs, said McKenzie Bay CEO Kevin Cook.

"I really think it's one of the more exciting technologies," Cook said. "The Ishpeming project has opened the door for a tremendous amount of interest."

A full update of progress on the Ishpeming turbine, including videos of the blades and animations of the lifting rig is available on the Web at www.mti-energy.com.



By JOHANNA BOYLE Journal Ishpeming Bureau
POSTED: January 18, 2010
http://www.miningjournal.net/page/content.detail/id/539276.html


January 8, 2010

Ishpeming UPDATE

View the Ishpeming update PDF file and associated video files through the links below:

Ishpeming Update

Blade Test Assembly video

Blade Lift animation

Blade Clamp Release animation
 


August 14, 2009

BETA BLADE ARRIVES

The first beta blade arrives for additional processing.  The new and improved blade will be foamed and skinned.  More developments to follow.


June 1, 2009

ISHPEMING PROJECT UPDATE

After completing extensive analysis of the “alpha” designed blades and a test lift in April, MTI has made a business and technical decision to produce and install a significantly re-designed “beta” blade. The beta blade more closely mirrors the production blade design, which will enable certification. The beta blade is more than 40 times stiffer than the alpha design enabling a more efficient installation and improvement in performance.

In addition, the review of the test lift has identified a less costly and faster method to hoist the blades atop the tower. A special lifting device has been designed and is being built that will result in a much improved lifting procedure.

Cranes will be relocated to another job until construction resumes. Blade delivery and installation completion dates are estimated at six to eight weeks.

April 17, 2009

MTI UPDATES ISHPEMING WINDSTOR WIND TURBINE INSTALLATION

BRIGHTON, MI – MTI Energy Management / Lighting Specialists has advised McKenzie Bay International Ltd (“MKBY:OTC.PK)that the WindStor® installation process at Pioneer Bluff Apartments in Ishpeming, Michigan continues to advance towards completion according to plan. MTI has taken many extra steps to ensure the successful completion of a renewable energy system where construction began and then delayed more than two years ago.

Most of the components that were not installed until this year have been in storage during this time.  To be certain that system integrity is maintained and safe operation is achieved; MTI is testing all parts and components multiple times during the completion process.  Testing has resulted in re-engineering parts and processes such as changing nuts and bolts to stainless steel, revising tolerances to higher standards, and identifying and correcting numerous oversights.

The blade installation is the final and most complex process requiring the greatest amount of planning and design. Thus far, one blade has been trial-lifted, temporarily installed, and taken back down.  MTI has conducted blade stress analysis tests based on the trial-lift and have determined that a custom-designed lifting support brace will be necessary for elevating the blades in a more efficient, less costly and safer manner.  A re-usable custom support brace is currently being designed and manufactured.  MTI anticipates the brace will be available in May for a successful completion.

MTI reports that an improved blade design, constructed of a composite material, will be utilized for future installations and will eventually replace the blades at Pioneer Bluff.  These blades will be implemented as soon as the manufacturing process is completed and a manufacturing source is identified.


April 6, 2009

The wind turbine installation continues to advance through planned steps at Pioneer Bluff Apartments and is nearing completion.

A trial blade installation was performed on Wednesday and Thursday last week. We are now making final adjustments to the blade installation and lifting process.

The next to last mechanical component to be installed is a German designed braking system. Technicians are awaiting visa approval for their entry into the USA to certify that the brake system meets their technical specifications.

Blade installation will proceed after final adjustments are completed and the installation of the braking system. We have completed all of our testing for this phase. Weather permitting the installation will proceed after the Easter holiday.


March 27, 2009

Turbine shaft Cap installation - the snow returns

 


March 26, 2009

More turbine shaft installation


March 25, 2009

More turbine shaft installation


March 24, 2009

Blade Preparation


 


March 20, 2009

Generator Installed & Turbine Shaft Installation in progress

One of the Village People

Extending Crane


March 18, 2009

McKenzie Bay International (MKBY), Settles MTI Lawsuit; Appoints New Board

 


March 9, 2009

Platform hoisting


 


March 3, 2009

Cranes arrive onsite

 


February 18, 2009

Blade sections unloaded in Ishpeming

 


February 17, 2009

Blades sections skinned, painted, loaded and shipped


 

January 12, 2009
 

Street Closing Approved for Construction Phase of wind turbine project at Pioneer Bluffs Apartments in Ishpeming.


December 22, 2008

Blade completion in process.  Happy Holidays!









Another shipment arrives


December 19, 2008

More components for the WindStor installation at Pioneer Bluffs in Ishpeming, MI are scheduled to arrive by truck on Monday, December 22, 2008.


December 16, 2008

Wind turbine nears completion

Pioneer Bluff in Ishpeming is ready to finish their form of alternative energy.

ISHPEMING -- After two years of waiting, a senior housing complex will soon be using cheaper, alternative energy.

Pioneer Bluff in Ishpeming received some of the parts that will complete their wind turbine project.

So far, only blade hubs and steel pipes have been delivered.

They'll be assembled to the tower sitting in front of the 88-unit apartment building.

MTI Energy, which took over the project, says it will provide 500,000 to 750,000 kilowatt hours a year and should take no more than a month to complete, weather permitting.

Watch video

Tuesday, December 16, 2008 at 6:04 a.m.
WLUC TV6 

Original link: http://www.uppermichiganssource.com/news/news_story.aspx?id=235932


December 16, 2008

Wind project getting off ground

By JOHANNA BOYLE, Journal Staff Writer

ISHPEMING - The wind turbine that will power the Pioneer Bluffs Apartments is one step closer to the start of construction.

The bulk of the two truckloads of equipment, which included the long inner and outer shafts of the turbine, arrived in Ishpeming Monday.

"I'm hoping to assemble in January," said Bryan Zaplitny, CEO of MTI Energy Management, the downstate company which designed the turbine. "We're sticking with it," despite predicted cold temperatures.

When fully constructed, the turbine will stand 90 feet above the already-built tower and will feature an 85-foot sphere to house the turbine blades.

In addition to Monday's deliveries, Zaplitny said four more trucks are expected, with two possibly arriving before Christmas.

One of the next shipments should include the turbine blades, which are being constructed, Zaplitny said. Once installed, the weather will not affect the blades' finish, he said. However, in extremely cold weather, workers will have to be careful during the unloading process when the turbines could be damaged.

Following the installation, the turbine will go through a series of tests, lasting about a month, before the apartment complex can begin to use the power, Zaplitny said.

The turbine will help lower the Pioneer Bluffs energy costs and will keep that energy rate stable for about 15 years, Zaplitny said. The turbine should produce 500,000 to 700,000 kilowatts annually.

Yalmer Mattila Contracting, the Houghton-based company that will be installing the turbine, plans to use a five- or six-person team to complete the assembly, said Jeremy Mattila, equipment operator for the company.

Although the project has been stalled for various reasons over several years, Zaplitny said Yalmer Mattila has been helpful and easy to work with.

"They've just been real good about everything. It instills a lot of faith in the people of the U.P. for sticking with it," he said.


Check out the video - Video Exclusive

By JOHANNA BOYLE, Journal Staff Writer
POSTED: December 16, 2008

Original story link:http://www.miningjournal.net/page/content.detail/id/519939.html?nav=5006


December 16, 2008

Wind turbine nears completion
Pioneer Bluff in Ishpeming is ready to finish their form of alternative energy.

ISHPEMING -- After two years of waiting, a senior housing complex will soon be using cheaper, alternative energy.

Pioneer Bluff in Ishpeming received some of the parts that will complete their wind turbine project.

So far, only blade hubs and steel pipes have been delivered.

They'll be assembled to the tower sitting in front of the 88-unit apartment building.

MTI Energy, which took over the project, says it will provide 500,000 to 750,000 kilowatt hours a year and should take no more than a month to complete, weather permitting.

Watch video

Tuesday, December 16, 2008 at 6:04 a.m.
WLUC TV6 

Original link: http://www.uppermichiganssource.com/news/news_story.aspx?id=235932


December 16, 2008

Wind project getting off ground

By JOHANNA BOYLE, Journal Staff Writer

ISHPEMING - The wind turbine that will power the Pioneer Bluffs Apartments is one step closer to the start of construction.

The bulk of the two truckloads of equipment, which included the long inner and outer shafts of the turbine, arrived in Ishpeming Monday.

"I'm hoping to assemble in January," said Bryan Zaplitny, CEO of MTI Energy Management, the downstate company which designed the turbine. "We're sticking with it," despite predicted cold temperatures.

When fully constructed, the turbine will stand 90 feet above the already-built tower and will feature an 85-foot sphere to house the turbine blades.

In addition to Monday's deliveries, Zaplitny said four more trucks are expected, with two possibly arriving before Christmas.

One of the next shipments should include the turbine blades, which are being constructed, Zaplitny said. Once installed, the weather will not affect the blades' finish, he said. However, in extremely cold weather, workers will have to be careful during the unloading process when the turbines could be damaged.

Following the installation, the turbine will go through a series of tests, lasting about a month, before the apartment complex can begin to use the power, Zaplitny said.

The turbine will help lower the Pioneer Bluffs energy costs and will keep that energy rate stable for about 15 years, Zaplitny said. The turbine should produce 500,000 to 700,000 kilowatts annually.

Yalmer Mattila Contracting, the Houghton-based company that will be installing the turbine, plans to use a five- or six-person team to complete the assembly, said Jeremy Mattila, equipment operator for the company.

Although the project has been stalled for various reasons over several years, Zaplitny said Yalmer Mattila has been helpful and easy to work with.

"They've just been real good about everything. It instills a lot of faith in the people of the U.P. for sticking with it," he said.


Check out the video - Video Exclusive

By JOHANNA BOYLE, Journal Staff Writer
POSTED: December 16, 2008

Original story link:http://www.miningjournal.net/page/content.detail/id/519939.html?nav=5006


December 11, 2008

The first two truckloads of components for the WindStor® installation at Pioneer Bluff Apartments in Ishpeming, Michigan are scheduled to arrive on Monday, December 15th, 2008.
 


December 8, 2008

Work to resume on wind turbine project

By JOHANNA BOYLE, Journal Staff Writer

ISHPEMING - Developers of the wind turbine project at Ishpeming's Pioneer Bluff Apartments hope to have the structure producing energy early next year.

Construction on the WindStor turbine, which was supposed to have been completed in 2006, should begin by the end of this month, according to the Ishpeming Housing Commission and MTI Energy Management CEO Bryan Zaplitny.

"We'd like to let everyone know we're moving forward," Zaplitny said.

Materials for the construction, including the turbine's blades, should be arriving in Ishpeming by Dec. 17, he said.

The project was stalled for the past two years due to a number of factors, he said. Although he would not discuss those factors in detail, Zaplitny said a lawsuit between MTI and McKenzie Bay and YA Global, two companies that were associated with MTI, was not the main factor.

"The issues are being straightened out," Zaplitny said.

Despite the cold weather, MTI is determined to get the project finished, Zaplitny said.

"I don't care if there's three feet of snow on the ground," he said. "That project will be done even in the harshest conditions."

Once it is functional, the turbine will provide cheaper alternative energy to the residents of the 88-unit senior housing complex, said Evelyn Valente-Heikkila of the Ishpeming Housing Commission. The agreement is that MTI erects the turbine free of charge and the apartment complex purchase the power created, Valente-Heikkila said.

"I'm pretty optimistic" it will be completed, she said.

Article Photos

The tower for the planned wind turbine sits in front of Pioneer Bluff Apartments, a senior housing complex in Ishpeming, in March 2007. MTI Energy Management said it will resume working on the turbine this month. MTI plans on having the turbine operational early next year. (Journal file photo)

Original article location: http://www.miningjournal.net/page/content.detail/id/519550.html?nav=5001


November 24, 2008

CLEAN GREEN ENERGY ADVANCES RENEWABLE ENERGY PROGRAM WITH LAS VEGAS AREA SCHOOL DISTRICT

MTI ENERGY MANAGEMENT / LIGHTING SPECIALISTS MOVES FORWARD WITH ISHPEMING, MI WINDSTOR® WIND TURBINE INSTALLATION


Brighton, MI, November 24, 2008 -- Clean Green Energy, LLC (CGE) (www.cleangreenenergyllc.com) advances forward with the Nevada Renewable Energy at Schools Pilot Program at the Clark County School District (CCSD) in Las Vegas.

A team of nine professionals engineering the project were in Las Vegas the week of November 17-21, 2008 and worked with CCSD facilities management, site engineering, and maintenance personnel. During this first of a series of scheduled trips to Las Vegas, the goal was to select specific sites for integrated solutions to rising energy costs. CCSD extended extraordinary cooperation to CGE professionals in supplying vital information necessary to facilitate a successful project.

Bryan Zaplitny, CGE President said, "We are extremely excited about this Project EverGREEN Schools™ renewable energy program for the Clark County School District. We believe that this could become a model for all school systems as a cost cutting, green energy generation and education solution throughout North America. This extraordinary opportunity, in conjunction with the WindStor® vertical axis wind turbine installation in Ishpeming, Michigan, has resulted in numerous inquires worldwide about green energy solutions."

Mr. Zaplitny, also CEO of MTI Energy Management / Lighting Specialists, Inc. (www.mti-energy.com ) further added, "MTI continues to move forward with the completion of the Ishpeming, Michigan, Pioneer Bluffs Assisted Living Community's, WindStor® wind turbine project. We met with contractors on Friday, November 14, 2008 and significant progress was made with the fine tuning of the electrical system, which will be the hub of the turbine's wind generation capability. Engineers and electrical contractors are prepared to accept system components and begin final assembly operations in December, 2008."

For more information - email cge@cleangreenenergyllc.com


Ishpeming Update
November 3, 2008

We are preparing to begin shipping the final components necessary to complete the WindStor® installation at Pioneer Bluff Apartments in Ishpeming, Michigan.  As components are transported to Ishpeming, we will post photos of the events.

We are taking these steps to be prepared to complete the installation as quickly as possible after breaking escrow from the closing of the McKenzie Bay and YA Global agreements.  Winter weather conditions will not prevent our completion of the installation.


October 16, 2008

McKenzie Bay International (MKBY), MTI Energy & YA Global Agree to Settlement
 


Component Parts for Completion


Posted 9/30/2008
Turbine shaft end section for blade attachment and turbine top end cover with plates


Posted 9/30/2008
Turbine shaft sections w/flanges


Posted 9/30/2008
Close up of turbine shaft sections w/flanges


Posted 9/25/2008


Posted 9/11/2008


CLEAN GREEN ENERGY SECURES PARTNERS GREEN ASSETS


Message from Bryan Zaplitny - President/CEO MTI


 

Updates regarding the WindStor project in Ishpeming Michigan
 

August 25, 2008


At the request of McKenzie Bay International Ltd, MTI is respecting this request by removing the previously posted reports of progress regarding settlement agreements signed on August 21, 2008.



 

MTI vs. MKBY / WindStor -- MTI Files Complaint 12-28-2007

Please review the verified complaint filed by MTI on Dec. 28, 2007 at the link below this statement. This action was necessary to state the facts, to move toward the completion of Ishpeming, to protect MKBY shareholders and their investments. The following points will give the readers of this announcement greater details.

  1. MKBY/Windstor management has refused to communicate in any way (meeting in person-requested by MTI several times, phone, email, fax) since October of 2007 with MTI.
     
  2. MTI has expended substantial amounts of time and resources to complete the Ishpeming project. However, at every step in this process, MKBY/Windstor has interfered in this completion.
     
  3. MKBY stock issuance to MTI was to be used at MTI’s discretion to reduce outstanding debt and to negotiate vendor contracts. MKBY owed suppliers and contractors for work completed, in progress, or to be completed in order to finish the Ishpeming project.
     
  4. MKBY not only tried to break the contract with MTI and recall the entire stock issuance, but they also would not allow their engineers to continue working with MTI to complete the Ishpeming project.
     
  5. Despite all that has transpired, MTI would like to complete the Ishpeming project. They have invested heavily into the project, have arranged completion agreements with suppliers and contractors, and have enhanced the project with other renewable energy elements (solar with Uni-Solar and energy storage with Cobasys) that MKBY had nothing to do with. Even though MTI was only the sales agent for MKBY, they have taken on responsibility of completing the project with the full cooperation of the existing Board of Directors (which is the existing management of Mckenzie Bay). The people of Ishpeming, the city and, especially, the housing commission, have waited patiently for this project to be completed and MTI wants to honor their loyalty and commitment by finishing what was started (and should have been completed) two years ago.

View MTI's complaint filed 12-28-07
(4.15 MB allow time to load)



Home : About MTI : Testimonials : LightScape: R.A.M.P. Program Contact Us : In The News

About Financing : New Products : Energy News : Our Mission

7627 Park Place Suite 101, Brighton, Michigan 48116
Phone: 248-446-9502  Fax: 248-446-9503
R.A.M.P. Program: 1-800-507-RAMP

1999 - 2007 © MTI Lighting Specialists. All rights reserved.   Privacy Statement